ClientPLN UIP3 Sulawesi
LocationGI Paniki and GI Tanjung Merah, North Sulawesi
Year2025
DisciplineElectrical – MV switchgear
Overview
The project
For PLN UIP3 Sulawesi, Spektrum delivered and installed new 20 kV cubicles for transformer 1 at the Paniki and Tanjung Merah substations (GI) in North Sulawesi, carried out under a joint operation (KSO) with PT PIM.
The work covered unloading and placing the cubicles, installation and wiring, and testing before the new line-up was put into service.