ClientPLN UIP3BS – UPT Palembang
LocationGI 150 kV Borang, Banyuasin, South Sumatra
Year2026
DisciplineElectrical – substation
Overview

The project

PLN UPT Palembang appointed Spektrum to replace the zigzag transformers for interbus transformers IBT#1 and IBT#2 at the 150 kV Borang substation (GI Borang) in Banyuasin, South Sumatra.

The work was carried out at an operating substation, so each step—from moving the new units into position to connecting the bushings—was coordinated with PLN’s substation team, ending with the planned energization of both transformers.

Step by step

How the work was done

Tap a photo to view it full size.

  1. Transformer arrival on site
    1

    Transformer arrival on site

    The new zigzag transformers were delivered to GI Borang.

  2. Transformer positioning
    2

    Transformer positioning

    Each unit was moved onto its foundation and set in position.

  3. Bushing connection work
    3

    Bushing connection work

    Our crew made the bushing and cable connections.

  4. Pre-energizing coordination
    4

    Pre-energizing coordination

    Final checks and coordination with the substation team before switching.

  5. Energizing
    5

    Energizing

    The zigzag transformers for IBT#1 and IBT#2 were energized and put into service.